Pre-Development

5621 Mildred Street

University of San Diego, San DiegoGround-up Development
8
Units
24 months
Timeline
University of San Diego
Neighborhood
Ground-up
Type
Investor access
Offering terms & documents

The opportunity

An infill development directly across from the University of San Diego — with additional projects already underway in the area, the team benefits from real scale and local execution efficiency.

The existing property is stabilized and tenant-occupied, generating income while the new 8-unit development moves through pre-development — the best of both phases: current cash flow, future upside.

Latest updates

Right-of-way nearly complete; groundbreaking targeted for late fallSep 2026

Right-of-way work is nearly finished and the Housing Commission documents have been drafted, approved, and are being notarized. Construction financing is in progress. Existing tenants are scheduled to move out in October, with the goal of breaking ground in November or December.

Income-producing while plans advanceAug 2026

Mildred Street's existing units remain fully tenant-occupied while design and entitlement work for the new development continues.

Milestones

✓
Property AcquiredDone
Closed on the property.
✓
Stabilized with Tenant in PlaceDone
Income-producing through pre-development.
✓
Soils & Survey TestingDone
Soils report and site survey.
✓
Architect Engaged · Preliminary DesignDone
Design team engaged; preliminary concepts underway.
✓
Schematics & MassingDone
Schematic design and massing studies.
✓
MEP ConsultantsDone
Mechanical, electrical, and plumbing design.
✓
Plans Packaged & Submitted to the CityDone
Full plan set submitted to the City of San Diego.
City Review CyclesIn Progress
Working through city plan-check comments.
Permits Stamped · RTIUpcoming
Permits approved — ready to issue.
Refinance into Construction LoanUpcoming
Construction financing in place; ready to build.
01Acquisition

The property as acquired, and the work that followed on the existing home.

02Renovation

The existing home, fully renovated and move-in ready.

03Design & Entitlement

Site plan, floor plans, and renderings from the plan set submitted to the City.